FAR 4.1001 says procurement instruments shall identify supplies or services as separately identified line items and, as needed, subline items. Each line item describes characteristics such as pricing, delivery, and funding. FAR 4.1005-1, except as provided in 4.1005-2, requires the schedule to show, as separate data elements, the line-item number, a description, a Product or Service Code, accounting classification, and, for fixed-price lines, unit of measure, quantity, unit price, and total price. Copy quantity and unit from those fields. Do not merge two CLINs into one supplier carton count.
If the cover says 80 each and a workbook says 8 cases of 10, do not pick a favorite. Open the amendment and the price sheet. AsherGate analysis keeps quantity, unit of measure, pack size, and ordering period in separate fields, shows Not found when a field is missing, and flags a quantity that looks converted from a pack or case count. Keep the source unit.
Options are not free extras. FAR 17.204 says the contract shall specify limits on additional supplies or services or the overall duration, including extensions, and shall state the period within which the option may be exercised. Options may appear as a percentage of line items, an increase in line items, or additional numbered line items. FAR 17.206 generally requires the contracting officer to evaluate option quantities or periods when it was determined before soliciting that the Government is likely to exercise them. Price the option CLINs the instructions name. Do not assume an unevaluated option can be ignored, and do not assume an option will be exercised.